Starting the first week of January, and lasting approximately 3 months, the Wakefield Bridge will close for demolition and reconstruction. The bridge is located on Wakefield Ave near the power plant, and crosses Richland Drainage District Ditch No. 4. Wakefield Ave will be closed to through traffic from Euclid Ave west to State Route BB/Brown Spur Rd. Access to the power plant and residences along Wakefield Ave will be maintained throughout the project.
Throughout Missouri, bridges are inspected every two years by MoDOT. After the most recent inspection of the Wakefield Bridge, the load limit was reduced from 40 tons to 10 tons due to deteriorating conditions caused by wear and tear on the bridge structure. The total replacement of the bridge is projected to cost $407,000, and 80% of that money is coming from MoDOT/FHWA Surface Transportation Program grants. The remaining $81,400 is coming from City of Sikeston funds.